Daily Production goals

Post by drtech » Wed Jun 06, 2018 10:47 am

Trying to figure out how to setup the new daily production goals in the appt view? (v18.1)
David Fuchs
Dentist - Springfield, MO
Smile Dental http://www.887-smile.com

User avatar
dgraffeo
Posts: 147
Joined: Wed Sep 24, 2014 3:19 pm

Re: Daily Production goals

Post by dgraffeo » Wed Jun 06, 2018 11:59 am

I'm not quite sure what you mean, but perhaps this would help: http://opendental.com/manual/productiontotals.html
"To understand what recursion is, you must first understand recursion."

David Graffeo
Open Dental Software
http://www.opendental.com

User avatar
drtech
Posts: 1647
Joined: Wed Jun 20, 2007 8:44 am
Location: Springfield, MO
Contact:

Re: Daily Production goals

Post by drtech » Thu Jun 07, 2018 12:10 pm

No, the manual is still for the old view...I am talking about the added field in beta 18.1 of "Daily Goals" BELOW that existing scheduled production on the appt Image
David Fuchs
Dentist - Springfield, MO
Smile Dental http://www.887-smile.com

tgriswold
Posts: 122
Joined: Fri Jun 07, 2013 8:52 am

Re: Daily Production goals

Post by tgriswold » Thu Jun 07, 2018 2:43 pm

We're still working on updating our documentation for the new beta version, but i'll try to summarize the feature here (I did not implement this feature so i'll do my best).

Production goals will be calculated by provider based on an hourly rate * scheduled hours for the provider, summed for all the providers in the Appt View. The user can add each provider production goal in the provider edit window "Hourly Production Goal". The production goal behaves the same as production, meaning providers must be added to the view in order to be considered.
Last edited by tgriswold on Thu Jun 07, 2018 2:55 pm, edited 2 times in total.
Travis Griswold
Open Dental Software
http://www.opendental.com

User avatar
cmcgehee
Posts: 711
Joined: Tue Aug 25, 2015 5:06 pm
Location: Salem, Oregon

Re: Daily Production goals

Post by cmcgehee » Thu Jun 07, 2018 2:43 pm

You can check back in with the manual in a few weeks. Our rule for ourselves is to document all features before they go to a stable release, so documentation for beta features is hit and miss.
Chris McGehee
Open Dental Software
http://www.opendental.com

noestervemb
Posts: 59
Joined: Sat Jul 09, 2016 7:45 am

Re: Daily Production goals

Post by noestervemb » Sun Jun 10, 2018 1:58 pm

I got it setup now but it only works if you check "show provider bars" we dont use this. So it now shows all these bars to the left that we dont use. Why does it require that to be shown? Is this an error?

User avatar
cmcgehee
Posts: 711
Joined: Tue Aug 25, 2015 5:06 pm
Location: Salem, Oregon

Re: Daily Production goals

Post by cmcgehee » Mon Jun 11, 2018 8:01 am

That's the way it's designed. That Daily Prod and Daily Goal are for the providers that are shown in the provider bars.
Chris McGehee
Open Dental Software
http://www.opendental.com

User avatar
irfan
Posts: 216
Joined: Thu Oct 21, 2010 9:09 am

Re: Daily Production goals

Post by irfan » Sat Aug 25, 2018 12:57 pm

has this been updated yet? the problem with this approach is that if you have multiple providers and they each have a bar, the goal calculates with them included even if they arent scheduled for that day or clinic.

User avatar
cmcgehee
Posts: 711
Joined: Tue Aug 25, 2015 5:06 pm
Location: Salem, Oregon

Re: Daily Production goals

Post by cmcgehee » Mon Aug 27, 2018 8:57 am

Yes, the manual is updated with a description of Production Goals: https://opendental.com/manual/productiontotals.html.
Irfan, the provider should only be included in goal calculating for the hours that are scheduled. Can you explain in more detail a situation where the calculation is incorrect?
Chris McGehee
Open Dental Software
http://www.opendental.com

User avatar
irfan
Posts: 216
Joined: Thu Oct 21, 2010 9:09 am

Re: Daily Production goals

Post by irfan » Sun Nov 25, 2018 10:40 am

Sorry to pull an old thread:

Chris,

We use clinics. I might be scheduled at clinic 3, but if my provider bar is shown on clinic 1 then i am added to the goal for clinic 1, even if i am not scheduled for any ops used in clinic 1. It seems to go by the schedule and not whether or not the provider is scheduled in any of the relevant ops.

User avatar
cmcgehee
Posts: 711
Joined: Tue Aug 25, 2015 5:06 pm
Location: Salem, Oregon

Re: Daily Production goals

Post by cmcgehee » Mon Nov 26, 2018 8:10 am

Let me look into this some more and get back to you.
Chris McGehee
Open Dental Software
http://www.opendental.com

User avatar
cmcgehee
Posts: 711
Joined: Tue Aug 25, 2015 5:06 pm
Location: Salem, Oregon

Re: Daily Production goals

Post by cmcgehee » Mon Nov 26, 2018 12:26 pm

Irfan, in order for Clinic 1 to not include your provider on the goal when you are only scheduled at Clinic 3, you should go the Appointment Module preferences and check "Appointment module production use operatories".
Chris McGehee
Open Dental Software
http://www.opendental.com