the new automation trigger "schedule procedure" only works when you use 'Make Appt', if you use appointment planner and copy the planned procedure to the pinboard the trigger does not work. I am trying to get everybody in the office to use appointment planner, that makes this automation useless.
Any workaround?

Dietmar

User avatar
jsalmon
Posts: 1551
Joined: Tue Nov 30, 2010 12:33 pm
Contact:

Re: 16.2 schedule procedure trigger does not work with plann

Post by jsalmon » Mon Sep 26, 2016 10:42 am

Verified that this is a bug. Adding to our bug tracker:
http://opendentalsoft.com:1942/ODBugTra ... sions.aspx
The best thing about a boolean is even if you are wrong, you are only off by a bit.

Jason Salmon
Open Dental Software
http://www.opendental.com

User avatar
jsalmon
Posts: 1551
Joined: Tue Nov 30, 2010 12:33 pm
Contact:

Re: 16.2 schedule procedure trigger does not work with plann

Post by jsalmon » Fri Sep 30, 2016 5:52 pm

The bug "Automation, the ScheduleProcedure trigger is not firing when scheduling the appointment via the Planned Appts tab in the Chart module." has been fixed and will be released with v16.2.54 and v16.3.11.
The best thing about a boolean is even if you are wrong, you are only off by a bit.